Gujarat RERA Project Registration Guide
To register a project on the Gujarat RERA Portal (https://gujrera.gujarat.gov.in), promoters need to follow these steps and provide the required details:
Step 1: Promoter Registration
Promoters must first create an account on the portal. The following information is required:
- Email ID: Used for project registration
- Mobile Number: Required for OTP verification
- PAN: Permanent Account Number
- Date of Incorporation: As per PAN
- Additional Requirements:
- ROF Certificate: For partnership firms (FORM G)
- CIN Registration Number: For companies
- LLPIN: For LLPs
- MOA & AOA: For companies
- Partnership Deed: For partnership firms
Note:
- Provide details for all key members:
- Company: All directors
- Partnership Firm: All partners
- LLP: All partners/entities
- Competent Authority/Government: All competent persons
- Other Entities: TRUST, HUF, AOP, BOI, and AJP members
- Include PAN card, photograph, email ID, mobile number, and address for each authorized signatory.
- Ensure all possible authorized signatories are entered while creating the account.
Step 2: Project Registration
After creating the user account, promoters must provide the following project details:
- Project Name
- Project Type: Residential, Commercial, Mixed, or Plotted
- Project Start & End Date
- Total Area of Land for Approved Layout
- Total Covered Area of Land
- Total Carpet Area
- Parking Details:
- Number and area of open and covered parking (certified by Engineer, Architect, and Promoter)
- Land Revenue Details:
- City Survey Number, TP Number (if applicable), and address
- Plan Approving Authority
- RERA Bank Details:
- As per RERA Banking Directions 2025
- Inventory Details:
- Type of inventory (flats/shops), number of units, carpet area, and area of balcony and terrace
- Internal Development Work:
- Water supply, roads, sewage and drainage, electrical supply, and solid waste management
- Other Internal Development Work:
- Lift, fire safety, renewable energy, etc.
- Add Professionals:
- Architect, Structural Engineer, CA, Contractor, and Agent
Step 3: Document Upload Requirements
1. Financial Documents:
- Balance Sheet, Profit & Loss Account, Cash Flow Statement, Director’s Report, Auditor Report, and ITR (Last 3 years)
2. FSI or TDR Documents:
- Any related documents and fees
3. Technical Documents:
- Approved building plan, layout plan, section plan, and area development plan (including sketch and Tippan plan)
- Brochure
- NOCs (Fire, Non-Agricultural, Airport, Environment Clearance, etc.)
- Project site photos and specifications
4. Legal Documents:
- Land Ownership Documents (7/12, property card, Gram Namuna, Encumbrance Certificate)
- Title Report and Certificate (Certified by an advocate with 10+ years of experience)
5. Affidavits:
- FORM B Declaration Drainage/Carpet Affidavit: By the promoter
- FORM B1 (Development Agreement): Affidavit by the promoter
- FORM B2 (Development Agreement): Affidavit by the promoter and landowners
6. Sale Documents:
- Performa for Sale Agreement, Draft Allotment Letter, and Draft Sale Deed
Step 4: Block Entry
Enter Commencement Certificate Number, Height of the Building, and FSI Used Area for each block
Step 5: Mapping the Project
Draw the entire project boundary (polygon)
Step 6: Assign Professionals
Link the professionals added earlier
Step 7: Form Submissions
- FORM 1: To be filled by the Architect
- FORM 2: To be filled by the Engineer
- FORM 3: To be filled by the CA
- These forms must be verified and accepted by the promoter
Step 8: Payment of Fees
Pay the calculated fees
Step 9: Document Submission
- Submit all documents along with the payment receipt and project application to the GUJRERA office within 7 days of payment.
Note: All area measurements must be in square meters (sq. m).